Olmsted CountyBoard Meeting Portal

File 2026-0419 · Consent · Public Works

Highway 22 Reconstruction — Change Order No. 3

Change order for unsuitable subgrade material encountered between stations 118+00 and 131+50.

Unsuitable subgrade material was encountered over approximately 1,350 feet. The change order covers excavation, geotextile separation and granular backfill. The unit prices are those bid in the original contract.

Recommendation

Approve Change Order No. 3 in the amount of $187,400.

Fiscal impact

$187,400, within the project contingency.